Navigation Links
The Construction Audit & Cost Control Institute Shares Ten Things to Consider When Contracting with MEP's on a GMP Basis
Date:3/30/2013

Dallas, Texas (PRWEB) March 30, 2013

The Construction Audit and Cost Control Institute (CAACCI) is recommending construction project owners take preventive measures to protect themselves from overcharges related to billable "costs" proposed by Guaranteed Maximum Price (GMP) subcontractors. Using a lump sum contract is a typical approach to contracting with mechanical, electrical or plumbing (MEP) subcontractors. But it may not always be the best way. Using a GMP contract for your MEP subcontractors offers a lot of the same benefits that are gained by using a GMP contract for the prime contractor.

Potential savings is one of the main advantages. However, these potential savings can disappear quickly depending on the contractual deal that is made with the MEP subcontractor. If your contract is not specific, you may end up paying much more to the GMP subcontractor than their true costs plus the agreed upon FEE.

Owners and their Construction Managers should consider the following ten point list of potential “hidden profit” problem areas before agreeing to the billable “costs” proposed by any GMP subcontractor:

1. Proposed FEE percentages for overhead and profit may exceed competitive FEE ranges for similar size jobs with similar commercial risks. For example, a proposed FEE of 21% would be considered excessive if the normal competitive FEE range for similar GMP MEP contracts would be 10% or less.

2. Proposed “Fixed Labor Rates” may be higher than actual wages plus actual labor burden by 10% to 50%.

3. Proposed “Fixed Labor Burden Cost Factors” may be higher than actual labor burden costs by 10% to 100%.

4. Proposed standard “discounted book” prices for commodity materials such as pipe, conduit, fittings, etc. may be 200% to 300% of actual commodity material costs.

5. Proposed “Equipment Rental Rates” on equipment owned by the Subcontractor may be 20% to 50% more than actual competitive third -party equipment rental rates for comparable equipment.

6. The GMP subcontractor may end up charging 2 or 3 times the fair market value (FMV) of a piece of subcontractor owned rental equipment unless the contract establishes a limit on “aggregate” bare rental charges. Note: If you plan to let the subcontractor keep the equipment after the job is over, consider establishing a cap on aggregate rental charges as a percentage of the FMV of the piece of equipment at the time it was brought to the job.

7. Proposed “shop burden markups” on shop-fabricated material or assemblies to be delivered to the job for installation may be higher than actual allowable and allocable overhead costs. Hidden profit in these markups may significantly offset the actual labor savings gained by not assembling work in the field.

8. Proposed charges for subcontractor “post-contract warranty” costs” may range from .5% to 1% of the GMP.

Note: Many owner’s draft contracts that state “warranty costs” are considered covered by the MEP subcontractor’s FEE rather than being allowed as a direct reimbursable “Cost of Work”.

9. Avoid the use of proposed lump sums for miscellaneous portions of scope of work to be performed by the GMP subcontractor. For example, avoid the use of paying proposed lump sum amounts for scope of work such as pre-construction design assist services and/or general conditions. By comingling lump sum and GMP work, the owner is taking a risk that costs attributable to the lump sum can be shifted to the Cost of Work billings effectively charging twice for the same costs.

10. Proposed use of related party sub-subcontractors using lump sum subcontracts arrangements rather than GMP sub-subcontract arrangements can result in hidden excessive profits by 10% to 50% due to a possible lack of meaningful competitive bidding. Note: Related party sub-subcontracts should be GMP contract arrangements with agreed upon limits on FEE payable to the related party sub-subcontractor.

Unless properly addressed, the impact of these potential “hidden profit” cost factors on a $50 Million cost plus fee GMP subcontract could improperly add $5 million to the amount paid to the GMP subcontractor.

These concepts and other key construction audit and cost control topics will be discussed in detail at the following construction audit seminar that will be held October 7-8, 2013 at the Dallas/Plano Marriott.

2 day Seminar - "Effective Auditing of Construction Activity"

The Construction Audit and Cost Control Institute (CAACCI) has been providing public offering and in-house professional development training seminars in affiliation with Courtenay Thompson & Associates since 2008. The principal instructors (Courtenay Thompson and Rich Townsend) have been providing construction audit and fraud professional development training to management and auditors for over 20 years.

For more information on the Construction Audit & Cost Control Institute please visit: http://www.caacci.org

Read the full story at http://www.prweb.com/releases/construction_audit/audit_training/prweb10583222.htm.


'/>"/>
Source: PRWeb
Copyright©2012 Vocus, Inc.
All rights reserved

Related medicine news :

1. Associated Plastic Surgeons & Consultants Reports that Insurance Denied Payment for Bilateral Breast Reconstruction Following Mastectomy
2. World Renowned Ear Reconstruction Surgeon Heralds New Technique
3. Dr. Polo to Offer Much-Anticipated, New Gummy Bear Implants for Superior Breast Augmentation and Breast Reconstruction
4. Oxblue Construction Cameras Help Two Universities Embarked on Major Building Projects Boost Stakeholder Confidence and Improve Project Management
5. Godsell Construction Corporation Aids Victims of Hurricane Sandy
6. PRMA Center for Advanced Breast Reconstruction to hold live online Breast Reconstruction Q&A
7. Round or shaped, implants yield good results in breast reconstruction
8. Breast Reconstruction Using Womens Own Tissue Appears Safe: Study
9. Parrish Construction Group Ribbon Cutting
10. 5-year follow-up - over half of all ACL reconstructions could be avoided
11. Sean Sullivan San Francisco Real Estate New Construction: Discusses ”The Heights” In Pacific Heights, 14 New Luxury Condos
Post Your Comments:
*Name:
*Comment:
*Email:
(Date:2/28/2017)... ... February 28, 2017 , ... In 2014, Harvard researchers ... studying approximately 800 deaths from prostate cancer, the researchers found that men who had ... likely to get fatal prostate cancer. Although the increased risks are small, they seem ...
(Date:2/28/2017)... ... , ... February is American Heart Month sponsored by The American Heart Association. ... cardiovascular health for themselves, their families and their communities. , Heart disease is ... deaths are caused by heart disease. Nearly half of all Americans have at least ...
(Date:2/28/2017)... ... ... BrightStar Care Marietta announced that it has received the 2017 Best of Home ... only to top-ranking home care providers, based on client satisfaction scores gathered by Home ... from across the country who have proven their ability to provide the highest quality ...
(Date:2/28/2017)... ... February 28, 2017 , ... ... from 4:30-5:30 p.m. at the 11th Annual RISE Nashville Summit. RISE Nashville is ... performance analytics, and engagement strategies. , The discussion will include best practices for ...
(Date:2/27/2017)... CA (PRWEB) , ... February 27, 2017 , ... ... muscle mass and overall body strength, which often leads to a host of ... Journal of the American Geriatrics Society discovered that good overall muscle ...
Breaking Medicine News(10 mins):
(Date:2/28/2017)... This report provides all the information you ... and activities since 2010. Download the full ... Deals and Alliance since 2010 report provides an in-depth ... world,s leading life sciences companies. On demand ... of the most up to date deal and company ...
(Date:2/28/2017)... 2017   Fourth-quarter 2016 ... $4,010 million to top end of guidance ... impairment charges in fourth-quarter 2016 associated with the write-down ... Company,s Generics reporting unit ... continuing operations; Full-year 2016 reported $14.48 diluted (GAAP) loss ...
(Date:2/27/2017)... Inc. (NYSE: HYH ) today reported fourth quarter ... related key planning assumptions. Executive Summary 2016 fourth ... compared to the prior year. Net income ... net income of $15 million in the fourth quarter of ... to adjusted net income of $27 million in the prior ...
Breaking Medicine Technology: